Suspended platform at the ESKA plant
Installation and dismantling of the QuikDeck system at a paper mill. The working platform provided access to the ceiling while allowing production activities to continue.
Project Execution
Work performed directly
on-site.
ESKA is a company based in the northern Netherlands that manufactures paper products. It is an older facility where an old asbestos-containing ceiling needed to be removed. The Quik Deck system proved to be an excellent solution for this project, as the work had to be carried out quickly and safely, without interrupting production operations.
We were tasked with installing and subsequently dismantling a total of 150m² of Quik Deck across 3 different locations within 5 days. A specialized asbestos-removal contractor removed the old ceiling material, leaving the ceiling exposed for repairs and subsequent work. The job went very well, and the client was highly satisfied ;).
This project was carried out in collaboration with http://skydeck-europe.eu/