Anode replacement on the Maersk Guardian
← All Projects

Denmark / Offshore and Marine

Anode replacement on the Maersk Guardian

Removal of old anodes and installation of new ones on the Maersk Guardian platform. Weld inspection using the MPI method and preparation of access for NDT inspectors.

Project Execution

Work performed directly
on-site.

Work in Denmark on the oil platform *Maersk Guardian* involved removing old anodes and installing new ones. All welds on the anodes had to be tested using the MPI (Magnetic Particle Inspection) method. We also performed additional tasks: replacing U-bolts and preparing rigging for NDT (Non-Destructive Testing) inspectors. For lifting the anodes, we utilized a specialized pulley system (up to 30 meters), while for higher sections of the structure, we worked in conjunction with a Palfinger system.